Austin Metro Line B Sewer Interceptor
GRIDBUILD FIELDCORE • MANAGING DIRECTOR COCKPIT

Executive Operations Cockpit

Strategic portfolio oversight, civil WBS burn rate, cash escrow retainage & project governance.

Notice to Proceed (NTP)
2026-01-15
Target Completion
2026-12-15
TOTAL CONTRACT VALUE
$14,850,000.00
Guaranteed Maximum Price (GMP)
PHYSICAL WBS PROGRESS
0% Completed
Earned: $0.00MTarget: $8.21M
BILLED TO CLIENT (GROSS)
$0.00
Pay Apps: 0Net: $0
10% ESCROW RETAINAGE
$0.00
Subcontractor retention reserve

Civil WBS Component Progress6 Major Scopes

Physical progress vs earned value per MasterFormat scope.

View Full DWP
02-200Trench Excavation & Shoring (12ft - 18ft Depth)
0 / 18,500 LF (0%)
Budget: $2,682,500Earned Value: $0Balance: $2,682,500
02-53024-Inch C900 DR-18 PVC Gravity Sewer Pipe
0 / 14,200 LF (0%)
Budget: $3,053,000Earned Value: $0Balance: $3,053,000
02-54030-Inch Class IV Reinforced Concrete Pipe (RCP)
0 / 4,300 LF (0%)
Budget: $1,268,500Earned Value: $0Balance: $1,268,500
02-60048-Inch Precast Concrete Sanitary Manhole Type-A
0 / 42 EA (0%)
Budget: $357,000Earned Value: $0Balance: $357,000
02-225Class I Crushed Limestone Pipe Bedding & Haunching
0 / 12,500 TON (0%)
Budget: $425,000Earned Value: $0Balance: $425,000
02-740TxDOT Type C Asphalt Surface Pavement Reinstatement
0 / 8,900 SY (0%)
Budget: $427,200Earned Value: $0Balance: $427,200

Recent Daily Ditch Logs

Superintendent entries awaiting executive awareness.

No Daily Logs Pending

No logs recorded yet. Once field crews submit station footage, they will appear here.